Norway's transmission system operator Statnett paused new grid reservations for data centers on 9 November, the same day the government announced a licensing scheme that will keep out new crypto mining. The grid reservation halt will last until at least August 2027, when a new system is set to come

<p>Norway's transmission system operator Statnett paused new grid reservations for data centers on 9 November, the same day the government announced a licensing scheme that will keep out new crypto mining. The grid reservation halt will last until at least August 2027, when a new system is set to come </p>